EnerPlastics has deployed a 521 kW Solar Project in Dubai as a step towards their sustainable initiatives.
- The plant is expected to generate annual energy of 838,000 kWh
- The PV plant will mitigate 360 tons of CO2 each year
- The Carbon Savings are equivalent to*:
The plant was built under an audited process involving DEWA approved consultant and contractor.
- Plant was constructed and commissioned under the expected timeline with 0 injury incidents.
- The project complies with the DEWA Shams policy wherein solar production will be utilized within the EnerPlastics facility, and any extra generation will be exported to DEWA as credits.